Sea Links Paving Schedule
 

The Sea Links Board wanted to provide you with the details for the upcoming paving project scheduled for Monday, May 19th and Tuesday, May 20th.

The contractor will be working in four main areas: the Park Entrance, Sawgrass, Wedgewood, and the Lower Gate Area. Their plan is to begin grinding and prep work on Monday morning, starting at the Park Entrance and moving sequentially through the other areas. All grinding and cleanup will be completed on Monday.

 Paving Schedule:

  • Monday: After the grinding/prep is completed, they will pave half of the Park Entrance and half of the Lower Gate Area – Leaving a lane open to allow traffic to continue flowing in and out of the park.

  • Tuesday: They will complete paving on Sawgrass, Wedgewood, and the remaining halves of the Park Entrance and Lower Gate Area.

During work hours (7:30 am to 7:30 pm), access to the roads will be limited. Once paving is complete each day, we ask that homeowners refrain from driving on the new pavement until the following morning to allow for proper curing.

Throughout the project, they will actively manage traffic and pedestrian flow by coning off work areas and providing on-site assistance to ensure safety for all residents.

Please feel free to reach out with any questions, concerns, or if special accommodations are needed for any residents.